SeeNews | 11 April 2019
ICSID tribunal rejects EVN claims for further compensation from Bulgaria
by Mario Tanev

EVN's claims were prompted by measures taken by the Bulgarian regulatory authorities and government agencies in connection with the pricing of electricity and the remuneration for public law obligations relating to renewable energy, EVN said in a statement on Wednesday.
EVN and Bulgaria reached an out-of-court settlement, under which part of the claims regarding the remuneration obligations for renewable energy were offset between a Bulgarian EVN subsidiary and the Bulgarian state-owned National Electricity Company.
"The decision of the arbitral tribunal can be challenged within 120 days before an ICSID Ad-hoc Annulment Committee for very limited reasons, which is currently being assessed by EVN," the company said.
The decision will not affect the consolidated results of the EVN Group.
"EVN AG considers itself a long-term investor in the Bulgarian market irrespective of the decision of the ICSID tribunal," the company underlined.
EVN, through its Bulgarian unit Power Distribution South, operates the power grid in southeastern Bulgaria.